More pipeline testing in Audrain County is scheduled to take place this upcoming Tuesday, April 9th.
According to an email from Energy Transfer they are hydro-testing to test the strength of the pipe to identify any area that may need repairs.
Officials say they have already identified 3 sections of the pipe that needs to be removed and replaced.
It is possible that nearby landowners may hear a noise if the line does not hold the water during hydro-testing, however officials say there is no cause for alarm.
A breach of the pipeline was reported during the most recent hydro-testing on Thursday, April 4th about 200 feet from where a break on March 3rd caused a massive explosion outside of Mexico along Highway 15.